The three core numbers
- PV (Planned Value) — budget for the work scheduled to be done by now.
- EV (Earned Value) — budget for the work actually done so far.
- AC (Actual Cost) — what we've actually spent.
Variances
- SV = EV − PV. Negative = behind schedule (we've earned less value than planned).
- CV = EV − AC. Negative = over budget (we earned less than we spent).
Performance indices
- SPI = EV / PV. < 1 = behind schedule. = 1 = on track. > 1 = ahead.
- CPI = EV / AC. < 1 = over budget. = 1 = on cost. > 1 = under.
↳ the why
Forecasting at completion
EAC (Estimate at Completion) projects total cost. Simplest formula: EAC = BAC / CPI (budget at completion divided by current cost performance index). If you're running CPI = 0.8, you'll likely finish 25% over budget at the current rate.